Fourth

05/21/22 -  The contractor has started cutting in grades which causes elevation differentials grade changes from hard surface to soft surface in the intersections. There are ramps installed for Main St., West Alley, Walnut, Oak, and at Wilcox and other driveways associated to the project. These changes will not be for long it’s just part of the process.

05/20/22 - DiPonio (the project contractor) will continue with roadway excavation and aggregate base installation. New concrete curb installation will take place this week, with flatwork possibly beginning at the end of the week. Inconveniences can be expected, there will be time frames where driveway access will become restricted due to the concrete installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.


05/13/22 - DiPonio (the project contractor) will continue with concrete removals, roadway excavation, and aggregate base installation. New concrete installation may occur towards the end of the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

05/06/22 - DiPonio (the project contractor) will continue with storm sewer installation, concrete removals, roadway excavation, and aggregate base installation. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/29/22 - DiPonio (the project contractor) will continue with utility work, including storm sewer, water main connections, and water service replacement, which will include scheduled events where you may be without water. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/18/22 - DiPonio (the project contractor) will continue with utility work, including storm sewer, water main connections, and water service replacement, which will include scheduled events where you may be without water for short period of time. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

04/01/22 - DiPonio (the project contractor) will continue with the installation of water main throughout the week. Work will include connections and water service replacement, which will include scheduled events where you may be without water. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.

03/28/22 - DiPonio (the project contractor) will continue with the installation of water main throughout the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day. 

03/21/22: - Diponio (the project contractor) will begin mobilizing equipment and material on Fourth St. beginning Monday 3/21. Pavement removal will take place in the middle of the week, Wednesday or Thursday, weather permitting. Installation of water main will begin at the end of the week. Inconveniences can be expected, there will be short time frames where driveway access may become restricted due to the underground utility installation on Fourth street. Traffic will be maintained for local traffic only, and access will be cleared accordingly at the end of the work day.